# Passive Fire General Process ## General Process: 1. Sub Contractors provide detailed penetration registers of what products they are proposing to use on site. 2. BCA Logic prepare detailed penetration Specification document after reviewing and approving fire sealing systems. 3. Each Contractor on each site will prepare their own detailed Photographic Penetration Register. 4. A sample wall and penetration sealing is built onsite. 5. BCA Logic hold a Tool Box talk with Clients site team and sub contractors. 6. First few units are completed and BCA Logic inspect. 7. Per level inspections undertaken. –Reinspection of defects is charged at hourly rate –back charged to sub contractors. 8. One appointed Client team member to coordinate this whole process - 1 point of contact 9. Each Contractor on each site will prepare their own detailed Photographic Penetration Register. 10. Each Contractor on each site will label all penetrations as per AS4072. 11. Each Contractor on each site will certify their own penetrations which will be incorporated into BCA Logic’s overall Certification Document. 12. Only the penetrations that BCA Logic Visually inspect and photograph ourselves will be included in our final Certification. 13. BCA Logic will use the Aconex Field Inspection Platform either provided for by Client for recording the inspections or provided by BCA Logic’s platform 14. Client site staff will preinspect each floor/area prior to calling BCA Logic staff to site as a  means of ensuring contractors works are in fact complete and ready for inspection.  15. All metal pipes will be wrapped with a fire rated wrap to both sides of wall penetrations and floor penetrations. 16. Electrical cables in EDB or Comms risers will also be wrapped with a fire rated wrap such as Promat Elite 1.5 FyreWrap or the Trafalgar Equivalent ## Design Principles: 1. Walls must be installed first before services – Critical this applies to: 1. Hebel Walls: - Hebel Walls must be installed before any other services are installed. - Hebel walls are only tested to be installed slab to slab not slab to timber roof as they must have a concrete base and head support structure consistent with Hebel Test Report. - No services can penetrate through Hebel metal top track all services penetrations must be through full Hebel material. - Cannot chase conduits into Hebel other than up to 11mm behind power outlet. ![[Pasted image 20250225121715.png]] 1. Plasterboard Walls ![[Pasted image 20250225121736.png]] 2. Masonry Walls 3. All service penetrations must be drilled / core holed neatly being  some 10mm larger than actual service going through Hebel wall – cannot smash hole with hammer 4. Horizontal bathroom / kitchen exhaust to façade avoids fire isolated riser shafts and fire damper installations. 5. Fire Dampers: 1. In Hebel musty have Hebel surrounding damper casing including over the top. 2. in Lightweight fire rated walls must have the fire rated plasterboard trimmed out as per below ‐photo before and after flange installed. ![[Pasted image 20250225121025.png]] # Passive Fire Issues (This will constantly be expanded) 1. [[Plasterboard Walls Must be Constructed First]] 2. [[Hebel Walls Must Be Constructed First]] 3. [[PVC Penetrations Must Be Cored]] 4. [[Services Installed Before Walls]] 5. [[Sealing Up Unused Cast In Collars]] 6. [[Top Track installed over Cast in Collars Flange]] 7. [[Unicollar Installation Around Pex Pipe]] 8. [[Poor Installation of Mastic Around Cables]] 9. [[Passive Fire Stopping for Metal Pipes]] 10. [[Sprinkler Pipe too close to other services]] 11. [[NBN Penetrations in Hebel Walls]] 12. [[NBN Conduits Cast Into Slab]] 13. [[Pair Coil Insulation Material]] 14. [[Electrical Riser Design Principles]] 15. [[Passive Fire Documentation]]