# Main Switchboard Sizes Spatial allowance is not adequate
### Issue Image:
![[Pasted image 20241120165951.png]]
## Issue Description:
- Spatial requirements by the Electrical Engineer are frequently Insufficient.
## Actions to Prevent this Issue:
- [ ] Architect to allow some extra space beyond what the Electrical engineer has requested.
- [ ] Builder to provide shop drawings of the Main Switchboard as soon as possible.
## Source
PAR75